এপিএসসিএল-এর মাস্টার প্ল্যান

Generation Plan of APSCL Up to 2041

 

Year

Installed Capacity (MW)

New Addition (MW)

Retirement Plan (MW)

Additional Increase (MW)

Total Generation (MW)

 
 

1

2

3

4

5=3-4

6=2+5

 

2023-2030

1647

120+450+1200+120=1890

53+195=248

1642

3289

 

* Raipura 120 MW Grid Tied Solar Power Plant (Phase-1)
* Ashuganj 450 MW CCPP (Replacement Project)
* Patuakhali 1200 (2×600) MW CCPP (Phase-1)
* Raipura 120 MW Grid Tied Solar Power Plant (Phase-2)

* Ashuganj 50 MW GEPP
* United Ashuganj 200 MW Modular Power Plant

 

2031-2041

3289

600+1200+600+100+600+1200+20=4320

223+383=606

3714

7003

 

* Ashuganj 600 MW CCPP (Replacement Project)
* Patuakhali 1200 (2×600) MW CCPP (Phase-2)
* Ashuganj 600 MW CCPP (Phase-1) at B-type Area
* Patuakhali 100 MWp Grid Tied Solar Power Plant
* Ashuganj 600 MW CCPP (Phase-2) at B-type Area
* Patuakhali 1200 (2×600) MW CCPP (Phase-3)
* Patuakhali 20 MWp Grid Tied Wind Power Plant

* Ashuganj 225 MW CCPP
* Ashuganj 450 MW CCPP South