Sl. No |
Name of the Power Plant |
Location |
Capacity |
Type of Fuel |
Commissioning Date |
Generation Plan of APSCL-2023 to 2030: |
|||||
1 |
Raipura 120 MW Grid Tied Solar Power Plant (Phase-1) |
Raipura. Narshindhi |
120 |
Sunlight |
2026 |
2 |
Ashuganj 450 MW CCPP (Replacement Project) |
Ashuganj, Brahmanbaria |
450 |
Natural Gas |
2028 |
3 |
Patuakhali 1200 (2×600) MW CCPP (Phase-1) |
Kalapara, Patuakhali |
1200 |
LNG (Imported) |
2029 |
4 |
Raipura 120 MW Grid Tied Solar Power Plant (Phase-2) |
Raipura. Narshindhi |
120 |
Sunlight |
2030 |
Sub Total = |
1890 |
|
|||
Generation Plan of APSCL-2031 to 2041: |
|||||
5 |
Ashuganj 600 MW CCPP (Replacement Project) |
Ashuganj, Brahmanbaria |
600 |
LNG (Imported) |
2031 |
6 |
Patuakhali 1200 (2×600) MW CCPP (Phase-2) |
Kalapara, Patuakhali |
1200 |
LNG (Imported) |
2034 |
7 |
Ashuganj 600 MW CCPP (Phase-1) at B-type Area |
Ashuganj, Brahmanbaria |
600 |
LNG (Imported) |
2037 |
8 |
Patuakhali 100 MWp Grid Tied Solar Power Plant |
Kalapara, Patuakhali |
100 |
Sunlight |
2038 |
9 |
Ashuganj 600 MW CCPP (Phase-2) at B-type Area |
Ashuganj, Brahmanbaria |
600 |
LNG (Imported) |
2041 |
10 |
Patuakhali 1200 (2×600) MW CCPP (Phase-3) |
Kalapara, Patuakhali |
1200 |
LNG (Imported) |
2041 |
11 |
Patuakhali 20 MWp Grid Tied Wind Power Plant |
Kalapara, Patuakhali |
20 |
Wind |
2041 |
Sub Total = |
4320 |
|