Sl. No

Name of the Power Plant

Location

Capacity
MW

Type of Fuel

Commissioning Date

Generation Plan of APSCL-2023 to 2030:

1

Raipura 120 MW Grid Tied Solar Power Plant (Phase-1)

Raipura. Narshindhi

120

Sunlight

2026

2

Ashuganj 450 MW CCPP (Replacement Project)

Ashuganj, Brahmanbaria

450

Natural Gas

2028

3

Patuakhali 1200 (2×600) MW CCPP (Phase-1)

Kalapara, Patuakhali

1200

LNG (Imported)

2029

4

Raipura 120 MW Grid Tied Solar Power Plant (Phase-2)

Raipura. Narshindhi

120

Sunlight

2030

Sub Total =

1890

 

Generation Plan of APSCL-2031 to 2041:

5

Ashuganj 600 MW CCPP (Replacement Project)

Ashuganj, Brahmanbaria

600

LNG (Imported)

2031

6

Patuakhali 1200 (2×600) MW CCPP (Phase-2)

Kalapara, Patuakhali

1200

LNG (Imported)

2034

7

Ashuganj 600 MW CCPP (Phase-1) at B-type Area

Ashuganj, Brahmanbaria

600

LNG (Imported)

2037

8

Patuakhali 100 MWp Grid Tied Solar Power Plant

Kalapara, Patuakhali

100

Sunlight

2038

9

Ashuganj 600 MW CCPP (Phase-2) at B-type Area

Ashuganj, Brahmanbaria

600

LNG (Imported)

2041

10

Patuakhali 1200 (2×600) MW CCPP (Phase-3)

Kalapara, Patuakhali

1200

LNG (Imported)

2041

11

Patuakhali 20 MWp Grid Tied Wind Power Plant

Kalapara, Patuakhali

20

Wind

2041

Sub Total =

4320